Reply To: Protection riddle no.8 – Risk of operation in power plant

#1211
Hamid

    Dear my friends, Your discussion is very useful for me. But according to commissioning report, even without any load current on that mentioned cable, they had measured more than 2A in secondary side of core balance CT. Regarding to cable length, I think that problem involved to AC cable capacitance current of three phase medium voltage cables. What is your opinion?