- This topic has 2 replies, 1 voice, and was last updated 3 years, 5 months ago by .
-
Topic
-
2700kVA 33000/1050 volt
Dd0 and Dy5 configeration cyclo convertor transformers generating large amounts of hydrogen gas. Various modificationd to the clamp config have been done the Dd0 as proven to be a succes but this hasnt worked on the Dy5.
The core clamps seem to be overheating and burning to the base of the transformer. What other tests/ modifications can be done to conclude this problem??
Viewing 2 replies - 1 through 2 (of 2 total)
Viewing 2 replies - 1 through 2 (of 2 total)