- This topic has 1 reply, 1 voice, and was last updated 3 years, 4 months ago by .
-
Topic
-
500MW power station under erection. Generator Transformer comes in separate phase banks.
Problem:As per design the vector group is Yd11 but on site Yd5 has arrived.
The LV side delta is made by Generator Bus Duct connections.
Solution:
1) Change Bus Duct connection. ( Much delay in commissioning activities)
2) Modifications done in protection circuits of Generator,GT,UAT. to accommodate this change groups.
Question:
Is it possible ? I need some more details as to how things were done.
Thanks
Viewing 1 replies (of 1 total)
Viewing 1 replies (of 1 total)
- You must be logged in to reply to this topic.